REPORT ON MANUFACTURING & TESTING OF POWER TRANSFORMERS
THE IDEAL TRANSFORMER VOLTAGE RATIO
A
power transformer normally consists of a pair of windings, primary and
secondary, linked by a magnetic circuit or core. When an alternating voltage is
applied to one of these windings, generally by definition the primary, a
current will flow which sets up an alternating m.m.f. and hence an alternating
flux in the core. This alternating flux in linking both windings induces an
e.m.f. in each of them. In the primary winding this is the ‘back-e.m.f.’ and,
if the transformer were perfect, it would oppose the primary applied voltage to
the extent that no current would flow. In reality, the current which flows is
the transformer magnetising current. In the secondary winding the induced
e.m.f. is the secondary open-circuit voltage. If a load is connected to the
secondary winding which permits the flow of secondary current, then this
current creates a demagnetising m.m.f. thus destroying the balance between
primary applied voltage and back-e.m.f. To restore the balance an increased
primary current must be drawn from the supply to provide an exactly equivalent
m.m.f. so that equilibrium is once more established when this additional
primary current creates ampere-turns balance with those of the secondary. Since
there is no difference between the voltage induced in a single turn whether it
is part of either the primary or the secondary winding, then the total voltage
induced in each of the windings by the common flux must be proportional to the
number of turns. Thus the well-known relationship is established that:
E1/E2=N1/N2
And,
in view of the need for ampere-turns balance:
I2/I1=N1/N2
Where
E, I and N are the induced voltages, the currents and number of turns
respectively.
E2/E1=N2/N1=K
This
constant K is known as voltage transformation ratio.
(a).If
N2>N1 i.e. K>1, then the transformer is called as STEP UP TRANSFORMER.
(b).If N2<N1
i.e. K<1, then the
transformer is called as STEP DOWN
TRANSFORMER.
Again
for ideal transformer Input=Output
(V1)(I1) = (V2)(I2)
[neglecting Iu ]
I2/I1=V1/V2=1/K
Where
I1 and I2 are primary and secondary currents.
Hence
the currents are in the inverse ratio of the transformation ratio.
STAGES OF POWER TRANSFORMER MANUFACTURING
1.
CORE
BUILDING
2.
UNLACING
OF CORE
3.
FITTING BOTTOM
INSULATION
4.
CORE
COIL ASSEMBLY AS PER DRAWING / ELECTRICAL SPECIFICATION
5.
FITTING
OF TOP INSULATION
6.
RELACING
OF CORE
7.
TERMINAL
GEAR MOUNTING
8.
VAPOUR
PHASING PROCESSING
9.
FINAL
TANKING AND OIL FILLING
10.
CASE
FITTING
11.
TESTING
12.
DESPATCH
TYPES
OF WINDING
The following are the types of winding used in
manufacturing of power transformer:
1.
R-S
COIL :
This is also known as the reverse section
coil. One section is given the reverse winding while one section is given the
forward winding. This can be manufactured in various sizes say five parallel or
two parallel conductors as suggested by the designer. The layer depth or LD of
the winding is defined as the number of turns to the number of segments
available in the section. Once the number of turn is given rest of the segment
in that section is provided with packing to maintain LD. Generally one to eight
numbers of conductors are used in this kind of winding.
2.
HELICAL COIL :
This kind of coil can be said to be winded
in shape of a spring. Here the numbers of conductors are more in numbers than
others and all are insulated from each other in order to reduce EDDY current
losses. Transposition in this kind of winding is done to make the conductors
equal in length so that no possibility of spark should be there due to
differences of voltages induced due to length of conductors. Two kinds of
transposition are usually done in this kind of winding:
a)
Section wise transpose
b) Three
numbers of transpose are provided in between conductor turns
3.
SPIRAL COIL :
This is the simplest kind of winding the
conductors are simply wounded on the base. The side from where the winding is
started is known as the start lead end where it is finished is known as the
finish lead.
4.
HALF SECTIONAL COIL:
These kind of coil can be classified on
basis of winding direction if the winding is started by rotation of conductors
in anticlockwise direction it is known as standard half sectional coil whereas
if the rotation is clock wise it is termed as non-standard half sectional coil.
The brazing leads required in some cases of the transformer are also provided
in this kind of winding.
5.
INTERLEAVED COIL:
In some cases the conductors
are wounded in such a fashion that the interleaved winding current rotates
in same conductor. When inter leaved
the number of conductor gets doubled than initial number. After
that section is made the
conductors are connected using entries.
6. COMPOSITE COIL: In this kind of winding
more than one conductor are winded with each other on the same machine. These
windings are generally used for the purpose of tapped coils.
CORE
CRGO (Cold
rolled grain oriented silicon steel) is used to build the core. The grain of
CRGO is oriented in the direction of rolling. The purpose of using CRGO is to
reduce the Hysteresis Losses. The thicknesses of these sheets are available
either in the dimension of 0.23mm or 0.27mm. The lamination on these sheets
minimizes the eddy current losses.
For core material, high-grade, grain oriented silicon
steel strip is used Connected by a core leg tie plate fore and hind clamps by
connecting bars. As a result, the core is so constructed that the actual
silicon strip is held in a sturdy frame consisting of clamps and tie plates,
which resists both mechanical force during hoisting the core-and-coil assembly
and short circuits, keeping the silicon steel strip protected from such force.
In large-capacity Transformers, which are likely to
invite increased leakage flux, nonmagnetic steel is used or slits are provided
in steel members to reduce the width for preventing stray loss from increasing
on metal parts used to clamp the core and for preventing local overheat. The
core interior is provided with many cooling oil ducts parallel to the
lamination to which a part of the oil flow forced by an oil pump is introduced
to achieve forced cooling. When erecting a core after assembling, a special
device shown in Fig. (8) Is used so that no strain due to bending or slip is
produced on the silicon steel plate
BURR
LEVEL: The sheets undergo proper cutting and is then available in many shapes
like Trapezoidal, octagonal and hexagonal e.t.c. but while cutting the edges of
these sheets, there is some generation of rough surfaces, these are known as
the burr level. The formation of these levels should be avoided as because they
produces air gap which increase the losses. To control the burr level cutting
of CRGO is done with the help of CNC (computer numeric control) machines.
Core
Building under Progress
Core building done on Three 65 T cradle, which ensures minimum jerk
during lifting of core
CORE
BUILDING
CORE
LAYOUT : The base is made
up of frames on which core is mounted as shown in the figure ,the top and end
frame and bottom end frame are connected as shown the level of the end frame
from the ground the limbs on which core is
mounted is also given mechanical support
- Transformer Core
Construction in which the iron circuit is
surrounded by windings and forms a low reluctance path for the magnetic flux
set up by the voltage impressed on the primary.
The steel strip surface is subjected to
inorganic insulation treatment.
All cores employ miter-joint core
construction. Yokes are jointed at an angle of 45° to utilize the magnetic flux
directional characteristic of steel strip. A computer-controlled automatic
machine cuts grain-oriented silicon steel strip with high accuracy and free of
burrs, so that magnetic characteristics of the grain-oriented silicon steel
remains unimpaired. Silicon steel strips are stacked in a circle-section. Each
core leg is fitted with tie plates on its front and rear side, with
resin-impregnated glass tape wound around the outer circumference. Sturdy
clamps applied to front and rear side of the upper and lower yokes are bound
together with glass tape.
And then, the resin undergoes
heating for hardening to tighten the band so that the core is evenly clamped.
Also, upper and lower clamps are connected by a core leg tie plate; fore and
hind clamps by connecting bars. As a result, the core is so constructed that
the actual silicon strip is held in a sturdy frame consisting of clamps and tie
plates, which resists both mechanical force during hoisting the core-and-coil
assembly and short circuits, keeping the silicon steel strip protected from
such force.
In large-capacity
Transformers, which are likely to invite increased leakage flux, nonmagnetic
steel is used or slits are provided in steel members to reduce the width for
preventing stray loss from increasing on metal parts used to clamp the core and
for preventing local overheat. The core interior is provided with many cooling
oil ducts parallel to the lamination to which a part of the oil flow forced by
an oil pump is introduced to achieve forced cooling.
0When erecting a core after
assembling, a special device is used so that no strain due to bending or slip
is produced on the silicon steel plate.
CORE-COIL
ASSEMBLY
After the unlacing of core is done i.e.,
the top yoke is removed, the core is made to stand erect and then the coils are
mounted on the core.
The coils as specified in the design may be
of following types:
1. L.V
COIL: This is known as low voltage coil. These coils are often referred to
as the primary coil for step down transformer. These coil are made in Order to
allow the flow of large current through it and thus the cross
Sectional area of the conductor used in
this kind of coil is larger and the numbers of turns per conductor are few,
also less number of conductors is used in L.V coil.
2. H.V
COIL: This is known as the high voltage coil. These coils are often
referred as the secondary coil of a step down transformer. These are made in
order to allow high voltages and hence small amount of current through it. So
the conductors used are smaller in size and number of turns per conductor
is more in numbers. Also the number of
conductor in this kind of coil increases.
3. T.V
COIL: This is known as the tertiary voltage coil.
4.
M.V COIL: This is known as the medium voltage coil.
As required or specified in the design at
the bottom of the core an insulator circular in shape is provided with blocks
made of wood attached on it . This is known as the block washer assembly the
wood attached on the waddman insulator material serves ducts, which help in
circulation of transformer oil and thus better cooling of transformer is
achieved. The core is also given a surrounding of a layer of waddman insulating
material on which spacers are provided which serves the purpose of creating
ducts for oil circulation as well as it gives support to the coil wounded on
it. Generally the L.V coil is mounted as the first layer after the spacers on
insulation material thereafter the coil is again shielded with the insulating
material and the spacers on which the H.V coil is mounted and this way the
process is carried on based on the design.
After the L.V and H.V coil are mounted on the core, the top of the core where
the mounting ends again the layer of wad man insulation material the block
washer assembly is provided. Now the job is taken for relacing.
PROCESSING AND DRY-OUT
The
paper insulation and pressboard material, which make up a significant
proportion by volume of transformer windings, have the capacity to absorb large
amounts of moisture from the atmosphere. The presence of this moisture brings
about a reduction in the dielectric strength of the material and also an
increase in its volume. The increase in volume is such that, on a large
transformer, until the windings have been given an initial dry-out, it is
impossible to reduce their length sufficiently to fit them on to the leg of the
core and to fit the top yoke in place.
The
final drying out is commenced either when the core and windings are placed or
when they are fitted into their tank, all main connections made, and the tank
placed in an oven and connected to the drying system. The tapping switch may be
fitted at this stage, or later, depending on the ability of the tapping switch
components to withstand the drying process.
VAPOUR
PHASE DRYING
The
main difference between conventional vacuum drying and vapour phase drying is
that, in the latter process the heat carrier is a vapour of low viscosity solvent more like kerosene,
with a sufficiently high flash point instead of air . The vapour is condensed
on the transformer and then re-evaporated in the plant. For this reason, vapour
phase installations include an evaporator and condenser system in addition to
the vacuum equipment and vacuum vessels associated with conventional drying
system which is applicable to transformers dried in the vacuum vessel as well
as in their own tank. The solvent heat conveyer system consists of storage, evaporation,
condensation, filteration, solvent feedback and control arrangement.
HEAT
CARRIER:
The solvent used should posses the following
properties for effective and efficient drying.
1. Vapour pressure must be distinctly below that of
water, so that a large pressure difference assists efficient water diffusion
from the beginning of the heating phase.
2. Evaporation heat should be as high as possible.
3. The presence of small amounts of the heat carrier
in the solid or oil insulation must have no effect on their ageing or general properties.
4. High ageing stability, allowing practically
unlimited use in the drying process. A solvent storage tank is normally
required to be refilled after few years.
5. Flame point should be above 55⁰C.
The following solvents meet the above characteristics
and are normally used in vapour phase drying systems.
1. Shellsol H (Shell)
2. Somenter T (Esso)
3. Varsol 60
4. Varsolene 60
5. Essovarsol 60 E
PHYSICAL HYDROCARBON AIR
PROPERTIES SOLVENT
1. Specific
density 0.785g/m
³ 1.25kg/m³
(Liquid) (Gaseous)
2. Molecular
weight 160 29
3. Heat of vaporization 306ҳ10³ Ws/kg ------
4. Specific
heat
2.09ҳ10³Ws/kg⁰C 1ҳ10³Ws/kg⁰C
(Liquid)
(Gaseous)
5. Inlet temperature
in 130⁰C 110⁰C
Vacuum vessel
6. Outlet
temperature from 90⁰C 90⁰C
Vacuum vessel at
the start of
Heating
7. Vapour
pressure at 130⁰C 140 torr -----
8. Energy
provided per mole 62.7ҳ
10³Ws 581ҳ10³Ws
9. Energy
provided per mole 179m³ at
130°C 31.4m³ at 110°C
10. Energy
released per m³
351ҳ10³Ws 18.4ҳ10³Ws
The drying process takes place in four stages as
mentioned
1. Preparation
2. Heating up and drying
3. Pressure reduction
4. Fine vacuum
1. PREPARATION (setting up): The entire evaporator and
condenser system is first evacuated to an absolute maximum pressure of 5 torr
by leakage air vacuum pump, before drawing the solvent into the evaporator and
heating it to the required temperature of 130⁰C.The vacuum vessel valves remain closed
during this operation.
In parallel
with the above preparatory steps, the vacuum system evacuates the vacuum vessel
containing the core and windings assembly to approximately to 5 torr. For
draining the condensate from the diverter switch oil compartment of on load tap
changer, wherever it is processed along with the transformer, and the drain
plug in the bottom of the compartment is opened. Vessel floor is at a
descending slope of1:100 towards the drainage system, so that no condensed
solvent remain inside the vessel. If tank containing core and windings assembly
is loaded into the vessel on a horizontal trolley, tank is also kept at a slope
of 1:100 to drain out the solvent from the tank.
2. HEATING UP AND DRYING: After the vessel is
evacuated, vessel heating is started and this heating is continued till the end
of fine vacuum phase. The vessel valves are opened at this stage, admitting
vapours of heat carrier in the vessel, most of which condense on which on cold
surfaces of the transformer. The condensed heat carrier is pumped back to the
evaporator through a filter. Heat released by the condensation gradually warms
up the insulation and mass component. Heat carrier vapour pressure in the
vessel and insulation moisture vapour pressure both increase with rising
temperature. As the water vapour pressure is considerably higher than that of
heat carrier, insulation moisture starts to evaporate at a low insulation temperature.
This produces mixtures of water vapour, leakage air and heat carrier vapour
inside the vessel, which is conveyed back to the condenser via the vapour
return in the condenser, whereas the leakage air discharges to the atmosphere
through the vacuum pump. The condensed water and heat carrier mixture is sent
into the collecting tank in which its component settle out under gravity. The
water gets collected in the bottom of tank due to higher specific weight, which
is measured periodically and drained off. Final insulation drying temperature
of 120-125°C is maintained for the time
required, to ensure full moisture evaporation from the deeper insulation
layers. Longer the heating phase, the shorter is the fine vacuum phase.
3. PRESSURE REDUCTION: The vapour supply remains
closed during this stage in which most of the heat carrier absorbed by the
insulation re-evaporates, condense out in the condenser and is finally returned
to the evaporator. This phase is terminated when an absolute pressure of 15 to
20 torr is reached in the vessel.
4. FINE VACUUM: This is the final drying stage, which
comes immediately after the pressure reduction phase. It is same as conventional
vaccum drying. The vessel is evacuated by the main vaccum system to a pressure
not exceeding 0.1 torr. This phase is terminated when water extraction rate is below
the desired level and insulation resistance and dissipation factor of windings
become constant.
After
drying of insulation by solvent vapours, other activities like oil
impregnation, soaking, draining, retanking redrying, completion of fittings, and
oil circulation follow in the same manner as for conventional drying with the
following exceptions.
i.
Since the transformer
is at a temperature of 125⁰C at the end of V.P.D., it is
cooled to a temperature depending upon the pressure in the vessel, such that
oil is neither vaporized nor oxidized during oil impregnation.
ii.
If only core and
windings assembly is dried without tank, the assembly is taken out from the
vessel and is immediately loaded into the tank. The tank is again kept in
vessel and oil is filled after evacuating vessel to the desired level removing
any moisture absorbed by the insulation due to exposure to the atmosphere.
OIL
IMPREGNATION
RECONDITIONING OF OIL:
Transformer oil is dehydrated and
de-aerated in the oil de-aeration plant. Regular sampling of transformer oil
shall be done from vessel for measurement of break down voltage.
The
value should be as following:
BDV
Below 72.5 kv
40 kv
(minimum)
(72.5-170) kv
50 kv (minimum)
170 kv & above 245
kv
60 kv (minimum)
The oil flow rate shall be such that the
pressure in the vessel at the end of oil impregnation doesn't exceed to more
than double of pressure at start of impregnation.
SOAKING:
Oil impregnated transformer shall be kept
under vacuum for a minimum of twelve hours for transformer of voltage class
above 145 kv and up to and including 245 kv. For 145 kV the transformer is kept
under atmospheric pressure for minimum of twelve hours. So that insulation is
completely soaked with oil.
DRAIN OUT:
After the above process the oil is pumped
out completely from the transformer to oil de-aeration plant.
ACCEPTANCE CRITERIA:
Rate of condensed water for six consecutive
measurements taken at an interval of one hour shall be within the limits given
below:
For Transformers condensate
rate (liter/hour)
(Above 145kv-245kv)
0.05
(Up to 145 kV) 0.10
FINAL TANKING/CASE FITTING
The job is finally put into
a tank in which various points are taken care of such as:
1. Dimension: the proper
tank dimension is achieved as specified in the design.
2. Weld leakage test: this
test is performed on the tank to check that whether any kind of leakage is
present in the tank or not.
3. Vacuum and pressure tests
are per formed on the tank to check its endurance.
Testing of Power Transformer
Tests
during manufacture
As
part of the manufacturer’s QA system some testing will of necessity be carried
out during manufacture. These are:
Core-plate
checks:
Incoming core
plate is checked for thickness and quality of insulation coating. A sample of
the material is cut and built up into a small loop known as an Epstein Square
from which a measurement of specific loss is made. (According to BS 6404-IEC
404)
Core-frame
insulation resistance: This
is checked by Megger and by application of a 2 kV R.M.S. test voltage on
completion of erection of the core. These checks are repeated following
replacement of the top yoke after fitting the windings. A similar test is
applied to any electrostatic shield and across any insulated breaks in the core
frames.
Core-loss
measurement: If there are any novel features
associated with a core design or if the manufacturer has any other reason to
doubt whether the guaranteed core loss will be achieved, then this can be
measured by the application of temporary turns to allow the core to be excited
at normal flux density before the windings are fitted.
Winding
copper checks: If continuously transposed
conductor is to be used for any of the windings, strand-to-strand checks of the
enamel insulation should be carried out directly the conductor is received in
the works.
Tank
tests: The first tank of any new design should be checked for
stiffness and vacuum-withstand capability. For 132 kV transformers, a vacuum
equivalent to 330 mbar absolute pressure should be applied. This need only is
held long enough to take the necessary readings and verify that the vacuum is
indeed being held for hours. After release of the vacuum, the permanent
deflection of the tank sides should be measured and should not exceed specified
limits, depending on length. Following this test, a further test for the
purpose of checking mechanical withstands capability should be carried out.
Typically a pressure equivalent to 3 mbar absolute should be applied for 8 hours.
The
tank is provided with an adequate number of smaller removable covers, allowing
access to bushing connections, winding temperature CTs, core earthing links,
off-circuit tapping links and the rear of tapping selector switches.
Tanks
must be provided with valves for filling and draining, and to allow oil
sampling when required. These also enable the oil to be circulated through
external filtration and drying equipment prior to initial energization on site,
or during service when oil has been replaced after obtaining access to the core
and windings. Lifting lugs or, on small units, lifting eyes must be provided,
as well as jacking pads and haulage holes to enable the transformer to be
maneuver on site.
Bushing connections
A
bushing is a means of bringing an electrical connection from the inside to the
outside of the tank. It provides the necessary insulation between the winding
electrical connection and the main tank which is at earth potential. The
bushing forms a pressure-tight barrier enabling the necessary vacuum to be
drawn for the purpose of oil impregnation of the windings. It must ensure
freedom from leaks during the operating lifetime of the transformer and be
capable of maintaining electrical insulation under all conditions such as
driving rain, ice and fog and has to provide the required current-carrying path
with an acceptable temperature rise. There is a current-carrying stem, usually
of copper, and the insulation is provided by a combination of the porcelain
shell and the transformer oil. Under oil, the porcelain surface creepage
strength is very much greater than in air, so that the ‘below oil’ portion of
the bushing has a plain porcelain surface. The ‘air’ portion has the familiar
shedded profile in order to provide a very much longer creepage path, a
proportion of which is ‘protected’ so that it remains dry in rainy or foggy
conditions.
At
33 kV and above, it is necessary to provide additional stress control between
the central high-voltage lead and the external, ‘earthy’ metal mounting flange.
This can take the form either of a synthetic resin-bonded paper multifoil
capacitor or of an oil-impregnated paper capacitor of similar construction.
This type of bushing is usually known as a condenser bushing.
CONCLUSION
To conclude power transformers are extensive device in today’s
world for transmission and distribution systems. A
device which could take the high-current, relatively low-voltage output of an
electrical generator and transform this to a voltage level which would enable
it to be transmitted in a cable of practical dimensions to consumers. BHEL is
one who’s manufacturing the transformers. Power transformer undergoes
several stages for manufacturing process. Tests are done to ensure the status
and reliability of the power transformer during as well as after
manufacturing.
These include
some major tests like:
1.
Impulse
Tests
2.
Temperature
Rise Tests
These four weeks
helped me a lot in gaining the knowledge of power transformer. It helps me to
learn the manufacturing process of power transformer. There are many auxiliary
types of equipment which are also used with transformer during operation or at
site which are also tested in BHEL.
It includes:
1.
Motor
Drive Unit
2.
RTCC
panels
No comments:
Post a Comment